In October of 2021, District 4 installed The RETEM System to repair an eroded ditch along I-75 near mile marker 67.
The 300 FT by 8 FT ditch required 36 YD3 of local Ready Mix. The RETEM System install began at 8:15 AM and was completed at 11:50 AM. The grading of the ditch was conducted the prior day.

The 3000-psi concrete was transported from the Ready Mix truck to the ditch with a backhoe.